What is the timeline for the project from start to completion?
In general, the development of a wind energy project can take up to four (4) years.
• January 2019: Request for Proposals is issued
• March 2019: Proponents shortlisted
• Summer 2019: Developer selected
• Summer 2019: Environmental assessments and community consultations begin
• 2020: Construction begins
• Late 2021/Early 2022: Commissioning and operations